TIMING, LOCATION AND REASONING OF TNMs (Also see Gantt chart)

Meeting 1 – Month 2 – Milan (IT): Kick-off meeting at lead partner, partners make a study visit to current situation at ELAZIG MTAL school. Start of A1 preparation and A2 Research phases of most IOs.

 

Meeting 2 – Month 6 – Badajoz (ES): meeting at Eolas office and study visits to 2 VET schools; end of A2 Research phase, start of A3 Development phase of most IOs.

 

Meeting 3 – Month 12 – meeting at Peiraias (EL); end of A3 Development phase of most IOs, start of alpha pilot testing, end of year 1 of project (reporting).

 

Meeting 4 – Month 18 – Leeuwarden (NL), end of A4 pilot test phase, review of feedback and improvement of output (A5) starts.

 

Meeting 5 – Month 24 – Elazig (TK): The day before our final Multiplier Event (the International Launch) we will have our final TNM as well to round up the project and discuss remaining points (incl. signign of final agreement on exploitation and sustainability).